Transmission Constraints Threaten to Curb India’s Renewable Energy Expansion

Syllabus: GS3/Renewable Energy/Infrastructure

Context

  • Insufficient transmission lines have emerged as a major obstacle to India’s rapid expansion of renewable energy capacity.

About

  • Close to 21 gigawatts (GW), that is about 9% of the country’s installed renewable energy capacity, is currently transferred from plants through temporary grid connections while awaiting dedicated transmission infrastructure.
    • Of this, around 12 GW faces restrictions on “power evacuation” during periods of peak solar generation. 
    • Power evacuation is the process of transferring electricity generated at a power plant to the consumption point.
  • During the financial year 2025-26 (FY26), around 6,900 gigawatt-hour (GWh) of clean electricity faced restrictions due to a mismatch between the rapid pace of renewable energy deployment and commissioning of associated transmission infrastructure. 
  • Industry executives also cautioned that these projects could turn into non-performing assets (NPAs) if the government doesn’t address the issue. 

Electricity Transmission

  • Electricity generated at a power plant has to travel through transmission lines before reaching distribution networks and ultimately consumers.
    • The basic chain is: From Renewable Energy Project to Transmission Network to Distribution Network and ultimately to Consumers.
  • India’s solar and wind capacity has expanded rapidly, but transmission infrastructure in some renewable-rich regions has not kept pace.
  • This is particularly important because India’s major renewable-energy resources are concentrated in specific regions.
    • Electricity generated in these regions may have to travel hundreds or thousands of kilometres to reach major demand centres.

Current Infrastructure for Grid Transmission

  • General Network Access (GNA) Framework: It is a temporary arrangement that allows renewable energy plants to use whatever spare transmission capacity is available while they wait for their permanent transmission connection.
    • T-GNA projects, however, can schedule power only if spare transmission capacity is available. 
  • Concerns: During periods of network congestion, long-term GNA projects receive priority, often resulting in curtailment of generation from T-GNA-connected plants.
    • The curtailment faced by these projects are as high as 70-80%  of their generating capacity, posing serious concern on project viability and debt servicing.
  • When the grid cannot accommodate all the electricity being generated, power generation may have to be deliberately reduced. This is known as power curtailment.

Why are Transmission Projects Taking Time?

  • Transmission infrastructure is more complicated and time-consuming to develop than generation capacity.
  • Major challenges include:
    • Land acquisition and Right of Way (RoW) issues.
    • Obtaining environmental and other statutory clearances.
    • Delays in construction of transmission lines and substations.
    • Procurement of specialised equipment.
    • Coordination between renewable-energy developers, transmission companies and governments.
    • Mismatch between the commissioning dates of renewable projects and transmission infrastructure.
  • This creates a situation where a renewable-energy project may be ready to generate electricity while its dedicated transmission system is still under construction.

Concerns: 

  • Power Curtailment: Insufficient transmission capacity can force renewable-energy plants to reduce generation, resulting in wastage of clean electricity.
  • Financial Stress: Curtailment reduces revenue for renewable-energy developers, making it difficult to service project debt and potentially discouraging future investment.
  • Grid Stability: The intermittent nature of solar and wind power, combined with inadequate transmission and storage, can create challenges in maintaining grid stability and balancing electricity supply and demand.
  • Delay in Renewable Targets: Transmission bottlenecks can slow the effective utilisation of India’s rapidly expanding renewable capacity, potentially affecting the achievement of its 2030 clean-energy and climate targets.

Government Initiatives

  • Grid Integration Plan: India’s grid is being reimagined through the ₹2.4 lakh crore Transmission Plan for 500 GW, linking renewable-rich states with demand centres.
    • The Government is prioritizing investment in transmission infrastructure through the Green Energy Corridors and new high-capacity transmission lines from Rajasthan, Gujarat, and Ladakh. 
    • While these projects are multi-year efforts, once operational they will unlock over 200 GW of new renewable capacity. 
  • Vision till 2032: Government has already planned for building High-Voltage Direct Current (HVDC) corridors and boosting inter-regional transmission capacity from 120 GW today to 143 GW by 2027, and 168 GW by 2032.
  • Incentives: Domestic manufacturing, incentivised through the Production-Linked Incentive (PLI) scheme, Domestic Content Requirement, imposition of duties, and duty exemptions for capital equipment, is reducing import dependency.
  • National Institute of Solar Energy (NISE): Offers training programs, workshops, and research support for solar PV, solar thermal, and hybrid technologies.
  • Capacity Building for State Nodal Agencies (SNAs): Training and technical support to state renewable energy agencies for project implementation, monitoring, and policy enforcement.
  • Research & Innovation Support: Funding for R&D in battery storage, hybrid projects, offshore wind, and green hydrogen.
  • International Cooperation & Training Programs: Collaboration with IRENA, GIZ, and other global agencies for knowledge exchange.
  • Deployment of Smart Grid Technologies: Advanced grid support technologies are planned to enhance voltage stability, improve system strength, and support reliable integration of renewable energy.

Conclusion

  • Over the past two years, policy attention has consciously shifted from pure capacity growth to system design.
  • These reforms mark a decisive step toward optimising transmission utilisation and fast-tracking stranded renewable projects, directly addressing one of the sector’s core implementation challenges.

Source: IE

 
Previous article India’s Coconut Sector

Other News of the Day

Syllabus: GS2/Polity Context Recently, the Supreme Court of India has upheld the constitutional validity of hanging as a mode of executing a death sentence, holding that the method does not violate the right to dignity under Article 21. About ‘Hanging as a Mode of Execution in India’ Hanging has been the principal statutory method of...
Read More

Syllabus: GS2/Governance  In News The Supreme Court is hearing a plea challenging the constitutional legality of polygamy under the Muslim Personal Law.  Polygamy It  is the practice of having more than one married spouse — wife or husband. Types:  Polygyny: One man having multiple wives. Polyandry: One woman having multiple husbands. Bigamy: Marrying another person...
Read More

Syllabus: GS3/Economy Context India’s coconut sector, deeply rooted in the country’s agricultural economy and cultural traditions, is steadily evolving from a predominantly traditional farming activity into a diversified, export-oriented industry. About Coconut  It is often described as the “Kalpavriksha” or “Tree of Life” because almost every part of the plant has economic or practical uses....
Read More

Idea of a ‘perfect victim’ or an ‘ideal victim’ Syllabus: GS2/Polity and Governance Context Bombay High Court set aside the 2021 judgment of the trial court that had acquitted Tarun Tejpal. The High Court also said that it had fallen for the notion that a sexual assault complainant must be a ‘perfect victim’ and conduct...
Read More
scroll to top